Timescales shown are purely illustrative; emboldening and indentation shows analysis levels
Task Name |
Duration (Days) |
Task Name |
Duration (Days) |
Stage 1 - Initiation |
8 |
Computer System |
1 |
Define and set Policy |
1 |
Networks |
1 |
Define the Project organisation |
1 |
Telecommunications |
1 |
Define Project control structure |
1 |
IT Security |
1 |
Develop Project plan |
1 |
Implement Risk reduction measures |
1 |
Define quality plan |
1 |
Implement Standby Arrangements |
6 |
Identify initial costs |
1 |
Negotiate third party recovery facilities |
1 |
Develop Project Initiation Document (PID) |
1 |
Enter into a contractual arrangement |
1 |
Agree PID |
1 |
Preparing and equipping the stand-by accommodation |
1 |
Purchase and install stand-by computer systems |
1 |
||
Stage 2 - Requirements Analysis & Strategy Definition |
13 |
Negotiate with external Service providers on their contingency plans |
1 |
Requirements |
6 |
Undertaking due diligence if necessary |
1 |
Identify critical processes |
1 |
Develop ITSCM plans |
1 |
Identify IT Service Support processes |
1 |
Develop Procedures |
1 |
Conduct Impact analysis |
1 |
Initial Recovery Testing |
3 |
Extract support requirements |
1 |
Component Testing |
1 |
Conduct Risk assessment & Vulnerability analysis |
3 |
System Testing |
1 |
Identify risks |
1 |
Integrated Testing |
1 |
Assess threat and vulnerability levels |
1 |
||
Assess the levels of risk |
1 |
Stage 4 - Operational Management |
29 |
Strategy |
7 |
Education and Awareness |
2 |
Determine risk reduction measures |
1 |
Establish Awareness Programme |
1 |
Determine recovery options |
4 |
Establish Education programme |
1 |
People and accommodation |
1 |
Training |
3 |
IT systems and networks |
1 |
Induction training |
1 |
Critical Services |
1 |
Management training |
1 |
Critical assets |
1 |
General staff training |
1 |
Analyse costs and benefits |
1 |
Review/Audit |
4 |
Make recommendations |
1 |
Establish review schedule |
1 |
Agree |
1 |
Establish review Terms of Reference |
1 |
Establish resource requirements |
1 |
||
Stage 3 - Implementation |
11 |
Establish feedback Process |
1 |
Organisation Planning |
3 |
Ongoing Testing |
4 |
Executive |
1 |
Establish test schedule |
1 |
Co-ordination |
1 |
Establish test scope and objectives |
1 |
Recovery |
1 |
Establish participants |
1 |
Implementation Planning |
11 |
Establish corrective process |
1 |
Emergency Response |
1 |
2 |
|
1 |
Review overall Change Control process |
1 |
|
Damage Assessment |
1 |
Ensure ITSCM is adequately covered |
1 |
Salvage |
1 |
Assurance |
2 |
Personnel |
1 |
Review ITSCM deliverables with Management |
1 |
Vital Records |
1 |
Review ITSCM process |
1 |
Accommodation and Services |
1 |
Table 7.2 -Example Project Plan
Example ITSCM Project Plan (To view this file correctly you will require Microsoft Project to be installed on your machine) |